Acquired wind farm in Hansford County, Texas with 240 MW interconnection and 114 MW nameplate capacity
Company: Marathon Digital
The claim, verbatim
Acquired wind farm in Hansford County, Texas with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity to establish behind-the-meter data center at low energy costs
Source (primary)
Marathon Digital 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We acquired a wind farm in Hansford County, Texas, with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity to establish a behind-the-meter data center at low energy costs.”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The 10-K's 2025 milestones list states each element of this claim, including the location and both capacity figures.
Confirmed in the source:
- MARA acquired a wind farm in Hansford County, Texas
- The wind farm has 240 MW of interconnection capacity and 114 MW of nameplate wind capacity
- The purpose was to establish a behind-the-meter data center at low energy costs
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000150760526000007/mara-20251231.htm) in full (412,365 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2026-03-02
Quote: “We acquired a wind farm in Hansford County, Texas, with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity to establish a behind-the-meter data center at low energy costs.”