Texas facility maximum power access capacity

Company: Hut 8 - Project: Beacon Point

Subject kind
facility capacity
Statement date
2026-09-01
Promised amount
1.0 GW
Current status
stated

The claim, verbatim

Texas data centre campus has access to up to one gigawatt of power

Source (primary)

Anthropic To Acquire Computing Power From Hut 8 - Yahoo Finance (-, news_article)
View cached copy (2026-09-02)Live source ↗Archive.org ↗

Quote: “The Texas data centre site is a sprawling 525-acre campus, with access to up to one gigawatt of power and an existing grid connection”

How we checked this

Attempted on September 15, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/anthropic-acquire-computing-power-hut-135600862.html) in full (7,696 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Anthropic To Acquire Computing Power From Hut 8 - Yahoo Finance

Quote: “The Texas data centre site is a sprawling 525-acre campus, with access to up to one gigawatt of power and an existing grid connection”

View cached copy (2026-09-02)Live source ↗Archive.org ↗