Data center facility in Texas
Company: Hut 8 - Project: Beacon Point
The claim, verbatim
Six data halls with 352 megawatts of critical IT capacity on approximately 521 acres in Nueces County, Texas
Source (primary)
Hut 8 8-K filed 2026-06-04 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗
Quote: “a turnkey data center, comprising six data halls with a combined total of 352 megawatts ("MW") of critical IT capacity, to be built on an approximately 521-acre property in Nueces County, Texas”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Hut 8 8-K filed 2026-06-04
Quote: “a turnkey data center, comprising six data halls with a combined total of 352 megawatts ("MW") of critical IT capacity, to be built on an approximately 521-acre property in Nueces County, Texas”