Promised amount
704.0 MW
Current status
stated

The claim, verbatim

Total contracted capacity at Beacon Point is 704 megawatts with same investment-grade tenant

Source (primary)

Hut 8 Stock Climbs After Securing Long-Term Nvidia AI Data Center Leases in Texas - TIKR.com (-, news_article)
View cached copy (2026-08-31)Live source ↗Archive.org ↗

Quote: “bringing the campus's total contracted capacity to 704 megawatts with the same investment-grade tenant”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/hut-8-stock-climbs-nvidia-ai-data-center-leases-texas) in full (8,812 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Hut 8 Stock Climbs After Securing Long-Term Nvidia AI Data Center Leases in Texas - TIKR.com

Quote: “bringing the campus's total contracted capacity to 704 megawatts with the same investment-grade tenant”