Texas campus completion adds 300 MW capacity
Company: CleanSpark
What the later record shows
Not a promise: a reported event · happened February 28, 2026
The claim, made in August 2026, reports a closing that had already happened in February 2026, so it is not a forward commitment. The date is set to the end of February because no exact day is given.
Checked October 11, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CleanSpark completed the closing on a second Texas campus during February, adding 300 megawatts of ERCOT-approved power capacity to its portfolio.
Source (primary)
CleanSpark Sells 553 Bitcoin in February, Eyes AI Infrastructure - CoinMarketCap (-, news_article)
View cached copy (2026-08-31)Live source ↗
Quote: “completed the closing on a second Texas campus during February, adding 300 megawatts of ERCOT-approved power capacity to its portfolio”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The article states that CleanSpark completed the closing on a second Texas campus in February, adding 300 megawatts of ERCOT-approved power capacity, which matches every element of the claim.
Confirmed in the source:
- CleanSpark completed the closing on a second Texas campus
- The closing occurred during February
- The campus added 300 megawatts of power capacity to CleanSpark's portfolio
- The added capacity is ERCOT-approved
What we did: Read our cached copy of the publisher (https://coinmarketcap.com/academy/article/cleanspark-sells-553-bitcoin-in-february-eyes-ai-infrastructure) in full (6,032 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark Sells 553 Bitcoin in February, Eyes AI Infrastructure - CoinMarketCap
Quote: “completed the closing on a second Texas campus during February, adding 300 megawatts of ERCOT-approved power capacity to its portfolio”