Operating power capacity across owned locations
Company: CleanSpark
The claim, verbatim
Total contracted power capacity of approximately 987 MW across Georgia, Mississippi, Tennessee and Wyoming
Source (primary)
CleanSpark 10-Q filed 2025-08-07 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “total contracted power capacity of approximately 987 megawatts ("MW") as of June 30, 2025”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The 10-Q states CleanSpark operates data centers in Georgia, Mississippi, Tennessee and Wyoming with total contracted power capacity of approximately 987 MW as of June 30, 2025.
Confirmed in the source:
- CleanSpark had a total contracted power capacity of approximately 987 MW as of June 30, 2025
- CleanSpark's data center locations are in Georgia, Mississippi, Tennessee and Wyoming
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000082787625000005/clsk-20250630.htm) in full (233,921 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 10-Q filed 2025-08-07
Quote: “total contracted power capacity of approximately 987 megawatts ("MW") as of June 30, 2025”