Mississippi data center capacity
Company: CleanSpark
The claim, verbatim
Mississippi facilities backed by approximately 63 MW supporting operational hashrate of 2.63 EH/s
Source (primary)
CleanSpark 10-K filed 2025-11-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “As of September 30, 2025, our Mississippi facilities have a developed data center infrastructure backed by approximately 63 MW, which supports an operational hashrate of 2.63 EH/s”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The Mississippi Operations section and the state table both give 63 MW and 2.63 EH/s.
Confirmed in the source:
- CleanSpark's Mississippi facilities were backed by approximately 63 MW as of September 30, 2025
- CleanSpark's Mississippi facilities supported an operational hashrate of 2.63 EH/s
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000119312525297510/clsk-20250930.htm) in full (562,147 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 10-K filed 2025-11-25
Quote: “As of September 30, 2025, our Mississippi facilities have a developed data center infrastructure backed by approximately 63 MW, which supports an operational hashrate of 2.63 EH/s”