Site pipeline capacity
Company: Cipher Mining
The claim, verbatim
Maintain pipeline of approximately 3.4 GW across seven sites in Texas and one additional site in Ohio
Source (primary)
Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We also maintain a pipeline of approximately 3.4 GW across seven sites in Texas and one additional site in Ohio.”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The 10-K states the roughly 3.4 GW pipeline and its seven-Texas-sites-plus-one-Ohio-site composition exactly as claimed.
Confirmed in the source:
- Cipher maintains a pipeline of approximately 3.4 GW of data center capacity
- The pipeline spans seven sites in Texas plus one additional site in Ohio
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) in full (477,779 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Cipher Mining 10-K filed 2026-02-24
Quote: “We also maintain a pipeline of approximately 3.4 GW across seven sites in Texas and one additional site in Ohio.”