Reveille interconnection approval

Company: Cipher Mining

Subject kind
regulatory
Statement date
2026-02-23
Promised amount
70.0 MW
Current status
stated

The claim, verbatim

Reveille Site has ERCOT interconnection approval of up to 70 MW with possibility for expansion

Source (primary)

Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Reveille Site has ERCOT interconnection approval of up to 70 MW, with the possibility for expansion.”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The filing states Reveille has ERCOT interconnection approval of up to 70 MW with the possibility for expansion.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) in full (477,779 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “The Reveille Site has ERCOT interconnection approval of up to 70 MW, with the possibility for expansion.”

View cached copy (2026-08-31)Live source ↗