jain.com

Polaris Forge 2 hyperscaler lease 200 MW

Company: Applied Digital - Project: Polaris Forge 2

Subject kind
customer
Statement date
2026-09-01
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

On October 22, 2025, entered into approximately 15-year lease with U.S.-based investment-grade hyperscaler for 200 MW of critical IT load at Polaris Forge 2.

Source (primary)

View 10-K (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “On October 22, 2025, we entered into an approximately 15-year lease with a U.S.-based investment-grade hyperscaler for 200 MW of critical IT load at the campus.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms View 10-K

Quote: “On October 22, 2025, we entered into an approximately 15-year lease with a U.S.-based investment-grade hyperscaler for 200 MW of critical IT load at the campus.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗