Polaris Forge 1 - First HPC data center operational
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Our first HPC data center at Polaris Forge 1, with approximately 100 MW of critical IT load, became operational in October 2025
Source (primary)
Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗
Quote: “Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 10-K filed 2026-07-29
Quote: “Our first HPC data center at the campus, with approximately 100 MW of critical IT load, became operational in October 2025.”
Record of changes
August 31, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 1, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.