Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2026-09-09
Promised amount
6600000000.0 USD
Current status
stated

The claim, verbatim

CleanSpark is constructing a data center campus in Sandersville, Georgia with $6.6 billion in contracted revenue over the contract term

Source (primary)

CleanSpark produces 593 BTC and sells 821 in August - Crypto News (-, news_article)
View cached copy (2026-09-09)Live source ↗Archive.org ↗

Quote: “CleanSpark said construction continued at its Sandersville, Georgia, data center campus. The company associates the project with $6.6 billion in contracted revenue.”

How we checked this

Checked on September 20, 2026. The cited source supports every part of this claim.

The document confirms ongoing construction at Sandersville and the $6.6 billion in contracted revenue over the contract term.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://crypto.news/cleanspark-produces-593-btc-and-sells-821-in-august/) in full (14,780 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark produces 593 BTC and sells 821 in August - Crypto News

Quote: “CleanSpark said construction continued at its Sandersville, Georgia, data center campus. The company associates the project with $6.6 billion in contracted revenue.”

View cached copy (2026-09-09)Live source ↗Archive.org ↗