245 MW critical IT capacity at River Bend data center
Company: Hut 8 - Project: River Bend
The claim, verbatim
The River Bend data center project will have 245 megawatts of critical IT capacity
Source (primary)
hut-8 8-K exhibit (tm2612880d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗
Quote: “finance the development and construction of a turnkey data center with 245 megawatts of critical IT capacity and the related substation at Hut 8's River Bend campus”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document states proceeds finance a turnkey data center with 245 megawatts of critical IT capacity at Hut 8's River Bend campus.
Confirmed in the source:
- River Bend data center project will have 245 megawatts of critical IT capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465926049810/tm2612880d1_ex99-1.htm) in full (7,554 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms hut-8 8-K exhibit (tm2612880d1_ex99-1.htm)
Quote: “finance the development and construction of a turnkey data center with 245 megawatts of critical IT capacity and the related substation at Hut 8's River Bend campus”