AMD 20 MW delivery
Company: Riot
What the later record shows
Outcome not yet confirmed
No passage mentions the AMD lease or delivery of the remaining 20 MW.
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Remaining 20 MW of initial AMD lease on track for May 2026 delivery
Source (primary)
riot 8-K exhibit (riot-20260430xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗
Quote: “Remaining 20 MW on track for May 2026 delivery”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The presentation lists 'First 5 MW phase delivered on schedule' and 'Remaining 20 MW on track for May 2026 delivery' under AMD Lease Execution, and shows the 25 MW initial lease with full deployment in May 2026.
Confirmed in the source:
- The AMD lease at Riot's Rockdale site has a 25 MW initial capacity, of which the first 5 MW phase was delivered
- The remaining 20 MW of the initial AMD lease was on track for delivery in May 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000110465926052943/riot-20260430xex99d2.htm) in full (38,944 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20260430xex99d2.htm)
Quote: “Remaining 20 MW on track for May 2026 delivery”