AMD Data Center Capacity Contract
Company: Riot
The claim, verbatim
AMD has exercised an option for an additional 25 megawatts of critical IT data center capacity, bringing total contracted capacity with AMD to 50 megawatts
Source (primary)
riot 8-K exhibit (riot-20260430xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗
Quote: “Announces AMD exercise of option for an additional 25 MW, bringing total contracted capacity to 50 MW of critical IT capacity”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document's headline and CEO statement confirm AMD exercised an option for an additional 25 MW, bringing total contracted capacity to 50 MW of critical IT capacity.
Confirmed in the source:
- AMD exercised an option for an additional 25 megawatts of data center capacity
- Total contracted capacity with AMD is 50 megawatts
- The capacity is described as critical IT capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000110465926052943/riot-20260430xex99d1.htm) in full (15,345 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20260430xex99d1.htm)
Quote: “Announces AMD exercise of option for an additional 25 MW, bringing total contracted capacity to 50 MW of critical IT capacity”