Live data center capacity
Company: Applied Digital
The claim, verbatim
175 MW of contracted capacity was live as of late July 2026
Source (primary)
Applied Digital Won't Collect Most of Its Rent Until 2029. I'd Wait to Buy the Stock. - The Motley Fool (-, news_article)
View cached copy (2026-09-08)Live source ↗Archive.org ↗
Quote: “And only 175 MW of the contracted capacity was live as of the company's late-July update.”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document states 175 MW was live as of the late-July update, and the Sept 2026 article context makes the year 2026.
Confirmed in the source:
- Only 175 MW of the contracted capacity was live as of the company's late-July update
What we did: Read our cached copy of the publisher (https://www.fool.com/investing/2026/09/07/applied-digital-won-t-collect-most-of-its-rent-until-2029-i-d-wait-to-buy-the-stock/) in full (11,518 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital Won't Collect Most of Its Rent Until 2029. I'd Wait to Buy the Stock. - The Motley Fool
Quote: “And only 175 MW of the contracted capacity was live as of the company's late-July update.”