Long Ridge capacity expansion path

Company: Marathon Digital - Project: Long Ridge

Subject kind
facility capacity
Statement date
2026-04-29
Promised amount
600.0 MW
Current status
stated

The claim, verbatim

MARA has multiple paths to expand capacity at the Long Ridge site to up to 600 gross MW through grid expansions and on-site power generation

Source (primary)

marathon-digital 8-K exhibit (d54802dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “MARA also has multiple paths to expand capacity at the site to up to 600 gross MW over time through a combination of grid expansions and on-site power generation”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms marathon-digital 8-K exhibit (d54802dex991.htm)

Quote: “MARA also has multiple paths to expand capacity at the site to up to 600 gross MW over time through a combination of grid expansions and on-site power generation”