jain.com

Reveille Q3 2027 energization target

Company: Cipher Mining - Project: Reveille Site

Subject kind
facility timeline
Statement date
2026-05-04
Promised by
2027-07-01
Current status
stated

The claim, verbatim

Reveille project is targeted for energization in Q3 2027.

Source (primary)

cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “2027 Q3 Target Energization”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document lists Reveille with a '2027 Q3 Target Energization'.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000025/exh992cipherdigital_busi.htm) in full (22,565 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (exh992cipherdigital_busi.htm)

Quote: “2027 Q3 Target Energization”

View cached copy (2026-09-08)Live source ↗