Dalton, GA CoreWeave site 175 MW with Phase 1 delivered, full completion early 2027

Company: Core Scientific - Project: Dalton 3

Subject kind
facility timeline
Statement date
2026-05-05
Promised by
2027-02-28
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Dalton, GA site with approximately 175 MW of leased power capacity contracted to CoreWeave has delivered Phase 1 (30 MW) with full completion expected by early 2027

Source (primary)

core-scientific 8-K exhibit (q1fy26earningsdeck.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The CoreWeave sites slide confirms Dalton, GA at ~175 MW, Phase 1 30 MW delivered, and full completion for early 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828026031246/q1fy26earningsdeck.htm) in full (14,867 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (q1fy26earningsdeck.htm)

Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”

View cached copy (2026-09-08)Live source ↗