Dalton, GA CoreWeave site 175 MW with Phase 1 delivered, full completion early 2027

Company: Core Scientific - Project: Dalton 3

Subject kind
facility timeline
Statement date
2026-05-05
Promised by
2027-02-28
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Dalton, GA site with approximately 175 MW of leased power capacity contracted to CoreWeave has delivered Phase 1 (30 MW) with full completion expected by early 2027

Source (primary)

core-scientific 8-K exhibit (q1fy26earningsdeck.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗

Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (q1fy26earningsdeck.htm)

Quote: “Dalton, GA Leased power: ~175MW Delivered Phase 1, a 30 MW site. Full completion on track for early 2027”