Lake Hawkeye Phase II expansion power capacity
Company: TeraWulf - Project: Lake Hawkeye
The claim, verbatim
Lake Hawkeye Phase II to expand to 300 MW of power availability
Source (primary)
terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗
Quote: “Phase I includes approximately 150 MW of power availability, expanding to 300 MW in Phase II”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (a_wulfearningsreleaseq1202.htm)
Quote: “Phase I includes approximately 150 MW of power availability, expanding to 300 MW in Phase II”