jain.com

Pennsylvania AI factory power capacity

Company: Nebius - Project: Pennsylvania AI Data Center Complex

Subject kind
facility capacity
Statement date
2026-05-12
Promised amount
1.2 GW
Current status
stated

The claim, verbatim

Nebius has secured up to 1.2 GW of power and land for a new, owned AI factory at a site in Pennsylvania

Source (primary)

nebius 8-K exhibit (tm2614392d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-07)Live source ↗

Quote: “has secured up to 1.2 GW of power and land for a new, owned AI factory at a site in Pennsylvania”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states Nebius secured up to 1.2 GW of power and land for a new, owned AI factory at a site in Pennsylvania, matching the claim exactly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465926059872/tm2614392d1_ex99-1.htm) in full (23,056 characters, retrieved September 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2614392d1_ex99-1.htm)

Quote: “has secured up to 1.2 GW of power and land for a new, owned AI factory at a site in Pennsylvania”

View cached copy (2026-09-07)Live source ↗