Pennsylvania AI factory

Company: Nebius - Project: Pennsylvania AI Data Center Complex

Subject kind
facility capacity
Statement date
2026-05-12
Promised by
2027-01-01
Promised amount
1200.0 MW
Current status
stated

The claim, verbatim

Pennsylvania AI factory with 1.2 GW power secured, to be delivered in phases beginning 2027

Source (primary)

nebius 8-K exhibit (tm2614392d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-07)Live source ↗

Quote: “we are announcing a new site in Pennsylvania where we have secured power for a deployment of up to 1.2 GW. The planned AI factory at this location will be delivered in phases beginning in 2027”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document confirms the Pennsylvania site's up-to-1.2 GW power and phased delivery starting 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465926059872/tm2614392d1_ex99-2.htm) in full (43,236 characters, retrieved September 7, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2614392d1_ex99-2.htm)

Quote: “we are announcing a new site in Pennsylvania where we have secured power for a deployment of up to 1.2 GW. The planned AI factory at this location will be delivered in phases beginning in 2027”

View cached copy (2026-09-07)Live source ↗