jain.com

Data center retrofit pipeline

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-06-09
Promised amount
1500.0 MW
Current status
stated

The claim, verbatim

Approximately 1.5 GW data center retrofit pipeline under management review with at least one near-term site acquisition targeted

Source (primary)

whitefiber 8-K exhibit (ea029430601ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-06)Live source ↗

Quote: “~1.5 GW Pipeline. Pipeline defined as data center sites for sale and under evaluation by management”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document lists a ~1.5 GW pipeline under management evaluation, characterizes it as a retrofit acquisition pipeline, and notes at least one near-term site acquisition is targeted.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390026067329/ea029430601ex99-1.htm) in full (24,487 characters, retrieved September 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea029430601ex99-1.htm)

Quote: “~1.5 GW Pipeline. Pipeline defined as data center sites for sale and under evaluation by management”

View cached copy (2026-09-06)Live source ↗