U.S. data center capacity for AMD deployments
Company: Core Scientific
The claim, verbatim
Core Scientific will provide more than 500 megawatts of U.S. data center capacity for AMD customer deployments beginning in 2027, with the ability to expand to 2.5 gigawatts
Source (primary)
core-scientific 8-K exhibit (amdpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗
Quote: “AMD secures more than 500 megawatts of U.S. capacity to support end customer deployments beginning in 2027, with the ability to expand up to 2.5 gigawatts”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document confirms the 500 MW U.S. figure beginning in 2027, the scaling to 2.5 GW, and that Core Scientific supplies the infrastructure.
Confirmed in the source:
- More than 500 megawatts of U.S. capacity will support AMD end customer deployments beginning in 2027
- The capacity can expand up to 2.5 gigawatts
- The infrastructure is Core Scientific's AI-ready infrastructure
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000183934126000012/amdpr.htm) in full (12,853 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms core-scientific 8-K exhibit (amdpr.htm)
Quote: “AMD secures more than 500 megawatts of U.S. capacity to support end customer deployments beginning in 2027, with the ability to expand up to 2.5 gigawatts”