Future capacity development targets
Company: Core Scientific
The claim, verbatim
Core Scientific has identified more than 2 GW of additional development opportunities to begin coming online between late 2028 and 2030
Source (primary)
Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal (-, news_article)
View cached copy (2026-08-31)Live source ↗
Quote: “Sullivan said Core Scientific has identified more than 2 GW of additional development opportunities that could begin coming online between late 2028 and 2030”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document quotes CEO Sullivan stating more than 2 GW of additional development could come online between late 2028 and 2030.
Confirmed in the source:
- Core Scientific has identified more than 2 GW of additional development opportunities
- These opportunities could begin coming online between late 2028 and 2030
What we did: Read our cached copy of the publisher (https://www.datacenterknowledge.com/deals/core-scientific-doubles-ai-capacity-to-1-1-gw-in-14b-amd-deal) in full (12,524 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal
Quote: “Sullivan said Core Scientific has identified more than 2 GW of additional development opportunities that could begin coming online between late 2028 and 2030”