2000.0 MW
Current status
stated

The claim, verbatim

Core Scientific has identified more than 2 GW of additional development opportunities to begin coming online between late 2028 and 2030

Source (primary)

Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “Sullivan said Core Scientific has identified more than 2 GW of additional development opportunities that could begin coming online between late 2028 and 2030”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document quotes CEO Sullivan stating more than 2 GW of additional development could come online between late 2028 and 2030.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.datacenterknowledge.com/deals/core-scientific-doubles-ai-capacity-to-1-1-gw-in-14b-amd-deal) in full (12,524 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific Doubles AI Capacity to 1.1 GW in $14B AMD Deal

Quote: “Sullivan said Core Scientific has identified more than 2 GW of additional development opportunities that could begin coming online between late 2028 and 2030”

View cached copy (2026-08-31)Live source ↗