jain.com

Colchis 1,000 MW target energization 2028

Company: Cipher Mining - Project: Colchis Site

Subject kind
facility timeline
Statement date
2026-08-03
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Colchis expected to energize 1,000 MW with 2028 target energization, with all necessary deposits funded and land secured

Source (primary)

cipher-mining 8-K exhibit (cipherdigital_businessup.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗

Quote: “2028 Target Energization (1) 1,000 MW Gross Capacity”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states Colchis is 1,000 MW with a 2028 target energization and that all necessary deposits are funded and land is secured.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm) in full (22,200 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (cipherdigital_businessup.htm)

Quote: “2028 Target Energization (1) 1,000 MW Gross Capacity”

View cached copy (2026-09-02)Live source ↗