Reveille 70 MW target energization Q3 2027
Company: Cipher Mining - Project: Reveille Site
The claim, verbatim
Reveille expected to energize 70 MW with target energization in Q3 2027
Source (primary)
cipher-mining 8-K exhibit (cipherdigital_businessup.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-02)Live source ↗
Quote: “2027 Q3 Target Energization 70 MW Gross Capacity”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
Stated verbatim in the Reveille section.
Confirmed in the source:
- Reveille has 70 MW gross capacity
- Target energization is Q3 2027
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm) in full (22,200 characters, retrieved September 2, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (cipherdigital_businessup.htm)
Quote: “2027 Q3 Target Energization 70 MW Gross Capacity”