Sandersville long-lead equipment procurement
Company: CleanSpark - Project: Sandersville
The claim, verbatim
Ordered and pre-paid all long-lead equipment items required to meet the Sandersville ready-for-service date
Source (primary)
cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-01)Live source ↗
Quote: “Ordered and pre-paid all long-lead items to meet Sandersville RFS date”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The document states all long-lead items were ordered and pre-paid to meet the Sandersville RFS date.
Confirmed in the source:
- Ordered and pre-paid all long-lead equipment items for Sandersville
- This was done to meet the Sandersville ready-for-service (RFS) date
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/827876/000119312526337999/clsk-ex99_1.htm) in full (17,538 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)
Quote: “Ordered and pre-paid all long-lead items to meet Sandersville RFS date”