The claim, verbatim

TeraWulf plans to pivot the former coal plant to natural gas to eventually support 1,000 megawatts of capacity to power a potential data center campus

Source (primary)

TeraWulf lands regulatory approval for first Maryland power plant purchase amid data center pivot - Technical.ly (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “eventually supporting 1,000 megawatts of capacity to power a potential data center campus”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states TeraWulf plans to convert the former coal plant to natural gas supporting 1,000 MW for a potential data center campus.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://technical.ly/civics/terawulf-lands-ferc-approval-maryland-power-plant/) in full (10,991 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf lands regulatory approval for first Maryland power plant purchase amid data center pivot - Technical.ly

Quote: “eventually supporting 1,000 megawatts of capacity to power a potential data center campus”

View cached copy (2026-08-31)Live source ↗