jain.com

Hancock County 340-megawatt hyperscale data center

Company: TeraWulf - Project: Hancock County Data Center

This claim was withdrawn on September 5, 2026. The article's encoded body text decodes to "TeraWulf wants to build a 482-megawatt hyperscale data center at the site of the former Century Aluminum smelter that halted operations in 2022," so the source states 482 MW rather than the claimed 340 MW.

How this was decided: Evidence review against the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2026-08-21
Promised amount
340.0 MW
Current status
withdrawn

The claim, verbatim

TeraWulf plans to build a 340-megawatt hyperscale data center at the site of the former Century Aluminum smelter in Hancock County

Source (primary)

TeraWulf commits to Beshear’s data center requirements - Daily Independent (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “TeraWulf wants to build a 340-megawatt hyperscale data center at the site of the former Century Aluminum smelter that halted operations in 2022”

How we checked this

Checked on September 18, 2026. The cited source supports part of this claim, but not all of it.

The article confirms the hyperscale project at the shuttered Hancock County Century Aluminum smelter, but it gives the size as 482 megawatts, not 340.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://www.dailyindependent.com/news/terawulf-commits-to-beshear-s-data-center-requirements/article_31b03dfb-fc1a-4edb-942b-c5501fe1e359.html) in full (8,809 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf commits to Beshear’s data center requirements - Daily Independent

Quote: “TeraWulf wants to build a 340-megawatt hyperscale data center at the site of the former Century Aluminum smelter that halted operations in 2022”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 4, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 5, 2026 — withdrawn