jain.com

704MW contracted IT capacity

Company: Hut 8 - Project: Beacon Point

Subject kind
facility capacity
Statement date
2026-09-01
Promised amount
704.0 MW
Current status
stated

The claim, verbatim

Beacon Point Data Center has 704MW of contracted information-technology capacity across two 352MW phases

Source (primary)

$35bn Anthropic Deal Ties Nvidia to Hut 8’s 1GW Beacon Point Data Center in Texas - Construction Review (-, news_article)
View cached copy (2026-09-04)Live source ↗

Quote: “The Beacon Point Data Center is a 704MW (352MW x 2) contracted information-technology facility”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The article calls Beacon Point a 704MW (352MW x 2) contracted IT facility with two 352MW development phases.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://constructionreviewonline.com/35bn-anthropic-deal-ties-nvidia-to-hut-8s-1gw-beacon-point-data-center-in-texas/) in full (10,668 characters, retrieved September 4, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms $35bn Anthropic Deal Ties Nvidia to Hut 8’s 1GW Beacon Point Data Center in Texas - Construction Review

Quote: “The Beacon Point Data Center is a 704MW (352MW x 2) contracted information-technology facility”

View cached copy (2026-09-04)Live source ↗