jain.com

PSC approves 482 MW grid connection

Company: TeraWulf

Subject kind
regulatory
Statement date
2026-08-21
Promised amount
482.0 MW
Current status
stated

The claim, verbatim

PSC approved TeraWulf to use an existing 482-megawatt connection to the grid

Source (primary)

KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU (-, news_article)
View cached copy (2026-08-31)Live source ↗Archive.org ↗

Quote: “The PSC approved TeraWulf to use an existing 482-megawatt connection to the grid.”

How we checked this

Attempted on September 14, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of the publisher (https://www.weku.org/the-commonwealth/2026-08-21/ky-utility-regulator-oks-electricity-contract-for-terawulfs-hancock-county-data-center-project?_amp\\u003dtrue) in full (11,588 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU

Quote: “The PSC approved TeraWulf to use an existing 482-megawatt connection to the grid.”

View cached copy (2026-08-31)Live source ↗Archive.org ↗