Beacon Point IT capacity leases

Company: Hut 8 - Project: Beacon Point

Subject kind
facility capacity
Statement date
2026-09-01
Promised amount
704.0 MW
Current status
stated

The claim, verbatim

Hut 8 has two 15-year leases at Beacon Point covering 704 megawatts of IT capacity

Source (primary)

Why Hut 8 Is Suddenly at Center of AI Boom - Blockonomi (-, news_article)
View cached copy (2026-09-03)Live source ↗Archive.org ↗

Quote: “Hut 8 previously disclosed two 15-year leases at Beacon Point covering 704 megawatts of IT capacity.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Why Hut 8 Is Suddenly at Center of AI Boom - Blockonomi

Quote: “Hut 8 previously disclosed two 15-year leases at Beacon Point covering 704 megawatts of IT capacity.”

View cached copy (2026-09-03)Live source ↗Archive.org ↗