Energy commodity swap contract for electricity hedging

Company: Marathon Digital

Subject kind
facility capacity
Statement date
2024-05-08
Promised by
2027-12-31
Current status
stated

The claim, verbatim

Acquired energy commodity swap contract hedging electricity price variability for data center operations, expiring December 31, 2027

Source (primary)

Marathon Digital 10-Q filed 2024-05-09 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company acquired a commodity swap contract as a result of its acquisition of GC Data Center Equity Holdings, LLC on January 12, 2024”

How we checked this

Checked on September 18, 2026. The cited source supports every part of this claim.

The filing says the swap came with the data center acquisition, hedges electricity purchase price variability, and expires December 31, 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000162828024022243/mara-20240331.htm) in full (181,234 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-Q filed 2024-05-09

Quote: “The Company acquired a commodity swap contract as a result of its acquisition of GC Data Center Equity Holdings, LLC on January 12, 2024”

View cached copy (2026-08-31)Live source ↗