Sandersville 150 MW expansion completion in 2023

Company: CleanSpark

This claim was marked delayed on November 21, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2023-08-10
Promised by
2023-12-31
Promised amount
150.0 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2024

The FY2023 10-K moved expected completion of the 150 MW Sandersville expansion to early in the fiscal quarter ending March 2024. In September 2024, an additional 50 MW there was still awaiting a utility transformer before going into service.

“The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”
2023-11-30 · CleanSpark 10-K filed 2023-12-01 View cached copy (2026-08-31)Live source ↗
“CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-09-22 · CleanSpark 424B3 filed 2024-09-23 View cached copy (2026-08-31)Live source ↗

Checked November 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Sandersville, Georgia site is undergoing a 150 MW expansion expected to be completed later in 2023.

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗

Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”

View cached copy (2026-11-21)Live source ↗

delays CleanSpark 10-K filed 2023-12-01

Quote: “The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”

View cached copy (2026-08-31)Live source ↗

delays CleanSpark 424B3 filed 2024-09-23

Quote: “CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 21, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 21, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.