Sandersville 150 MW expansion completion in 2023
Company: CleanSpark
What the later record shows
The date slipped · new target March 31, 2024
The FY2023 10-K moved expected completion of the 150 MW Sandersville expansion to early in the fiscal quarter ending March 2024. In September 2024, an additional 50 MW there was still awaiting a utility transformer before going into service.
“The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”
2023-11-30 · CleanSpark 10-K filed 2023-12-01 View cached copy (2026-08-31)Live source ↗
“CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”
2024-09-22 · CleanSpark 424B3 filed 2024-09-23 View cached copy (2026-08-31)Live source ↗
Checked November 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Sandersville, Georgia site is undergoing a 150 MW expansion expected to be completed later in 2023.
Source (primary)
cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗
Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)
Quote: “The site is undergoing a massive 150 MW expansion with expected completion later this year.”
delays CleanSpark 10-K filed 2023-12-01
Quote: “The site is undergoing a 150 MW expansion with expected completion early in our second fiscal quarter ending March 2024.”
delays CleanSpark 424B3 filed 2024-09-23
Quote: “CleanSpark has completed an additional 50 MW of data center infrastructure in Sandersville, GA, which is pending the commissioning of a utility transformer before it goes into service”