16 EH/s hashrate target by end of 2023

Company: CleanSpark

Subject kind
guidance
Statement date
2023-08-10
Promised by
2023-12-31
Current status
verified

What the later record shows

Delivered; the record does not say when

No passage gives CleanSpark's hashrate at the end of calendar 2023. The 2025 10-Q shows an average of 20.4 EH/s for the period ending June 30, 2024, so 16 EH/s was passed by mid-2024, but on-time versus late cannot be told.

“CleanSpark average hashrate (in terms of EH/s) (3) 45.3 20.4”
2025-08-06 · CleanSpark 10-Q filed 2025-08-07 View cached copy (2026-08-31)Live source ↗

Checked November 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CleanSpark projects reaching 16 EH/s of hashrate by the end of calendar year 2023.

Source (primary)

cleanspark 8-K exhibit (clsk-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗

Quote: “~150,000 Operational Miners 16 EH/s PROJECTED END OF CALENDAR YEAR 2023”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cleanspark 8-K exhibit (clsk-ex99_1.htm)

Quote: “~150,000 Operational Miners 16 EH/s PROJECTED END OF CALENDAR YEAR 2023”

View cached copy (2026-11-21)Live source ↗

confirms CleanSpark 10-Q filed 2025-08-07

Quote: “CleanSpark average hashrate (in terms of EH/s) (3) 45.3 20.4”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 21, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 21, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.