5.5 EH/s and 160 MW operational at June 30, 2023
Company: TeraWulf
The claim, verbatim
At June 30, 2023, total operational hashrate had reached 5.5 EH/s across 160 MW of capacity at the two sites. The fleet was about 50,000 miners.
Source (primary)
terawulf 8-K exhibit (wulf-20230814xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗
Quote: “The Company's total operational hash rate increased to 5.5 EH/s and 160 MW of capacity across its two sites.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulf-20230814xex99d1.htm)
Quote: “The Company's total operational hash rate increased to 5.5 EH/s and 160 MW of capacity across its two sites.”