NVIDIA H200 GPU purchase

Company: IREN

Subject kind
acquisition
Statement date
2024-09-15
Promised by
2024-12-31
Promised amount
43900000.0 USD
Current status
verified

What the later record shows

Delivered; the record does not say when

By June 30, 2025 the AI Cloud fleet included H200 GPUs, totalling about 1.9k H100 and H200 GPUs, so the H200s were delivered. No passage says whether commissioning happened in Q4 2024.

“Our AI Cloud Service, comprising NVIDIA H100 and H200 GPUs as of June 30, 2025, is also currently operated at our Prince George site.”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
“as of June 30, 2025, we had approximately 1.9k NVIDIA H100 and H200 GPUs, which are deployed at our Prince George data center”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company purchasing 1,080 NVIDIA H200 GPUs for $43.9 million with delivery and commissioning expected during Q4 2024

Source (primary)

IREN 6-K filed 2024-09-16 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company is purchasing 1,080 of the latest-generation NVIDIA H200 GPUs for $43.9m, with delivery and commissioning expected during 4Q 2024.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 6-K states the company is purchasing 1,080 NVIDIA H200 GPUs for $43.9m, with delivery and commissioning expected in 4Q 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1878848/000187884824000012/a6-knvidiah200purchase.htm) in full (2,975 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN 6-K filed 2024-09-16

Quote: “The Company is purchasing 1,080 of the latest-generation NVIDIA H200 GPUs for $43.9m, with delivery and commissioning expected during 4Q 2024.”

View cached copy (2026-08-31)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “Our AI Cloud Service, comprising NVIDIA H100 and H200 GPUs as of June 30, 2025, is also currently operated at our Prince George site.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.