Acquire 16.5 MW bitcoin mining facility in Clinton, MS
Company: CleanSpark
The claim, verbatim
Entered into definitive agreements to acquire 16.5 megawatts of bitcoin mining facilities in Clinton, Mississippi
Source (primary)
CleanSpark 8-K filed 2024-09-17 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “entered into definitive agreements to acquire 16.5 megawatts of bitcoin mining facilities in Clinton, Mississippi for a total purchase price of up to $5,775,000”
How we checked this
Checked on September 17, 2026. The cited source supports every part of this claim.
The 8-K states that CleanSpark's subsidiary entered into definitive agreements to acquire 16.5 megawatts of bitcoin mining facilities in Clinton, Mississippi.
Confirmed in the source:
- CleanSpark's subsidiary CSRE Properties Mississippi, LLC entered into definitive agreements on September 16, 2024
- The agreements are to acquire 16.5 megawatts of bitcoin mining facilities
- The facilities are in Clinton, Mississippi
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017024107034/clsk-20240916.htm) in full (6,092 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 8-K filed 2024-09-17
Quote: “entered into definitive agreements to acquire 16.5 megawatts of bitcoin mining facilities in Clinton, Mississippi for a total purchase price of up to $5,775,000”