Total Canada & USA capacity after Childress Phase 1
Company: IREN
What the later record shows
Delivered late · happened June 30, 2024
Total operating capacity was 220MW in March 2024 and 245MW in May 2024. It reached 260MW, at about 10 EH/s, as of June 30, 2024, which is after the March 31, 2024 target.
“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
After the Childress 80MW expansion, total capacity across Canada and the USA is planned at 260MW, up from 180MW operating. This supports hashrate growth from 5.6 EH/s to 9.1 EH/s, assuming purchase of Bitmain S19 XP miners, which have not yet been purchased.
Source (primary)
iren 8-K exhibit (brhc20058546_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗
Quote: “Supports hashrate growth from 5.6 EH/s to 9.1 EH/s 6”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The capacity table shows 180MW operating and 260MW in total. A footnote states that the 9.1 EH/s figure assumes S19 XP miners that have not yet been bought.
Confirmed in the source:
- Total operating capacity across Canada and the USA is 180MW (5.6 EH/s)
- Total capacity across Canada and the USA after the Childress 80MW expansion is 260MW (9.1 EH/s)
- The expansion supports hashrate growth from 5.6 EH/s to 9.1 EH/s
- The hashrate figure assumes purchase of Bitmain S19 XP miners
- Those additional miners have not yet been purchased
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036123042844/brhc20058546_ex99-1.htm) in full (16,412 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (brhc20058546_ex99-1.htm)
Quote: “Supports hashrate growth from 5.6 EH/s to 9.1 EH/s 6”
confirms IREN 20-F filed 2024-08-28
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”