jain.com

30 EH/s Bitcoin mining program

Company: IREN

Subject kind
guidance
Statement date
2023-10-04
Current status
stated

The claim, verbatim

The company is pursuing a 30 EH/s Bitcoin mining program via single-site expansion at Childress; 30 EH/s is the illustrative hashrate if Childress is fully built out to 600MW, assuming purchase of S19 XP miners not yet purchased.

Source (primary)

iren 8-K exhibit (ef20012021_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗

Quote: “30 EH/s Bitcoin mining program o Single site expansion, ongoing delivery and construction process”

How we checked this

Checked on November 20, 2026. The cited source supports every part of this claim.

The strategic highlights describe a 30 EH/s single-site expansion program. A footnote explains it as the illustrative hashrate for a full 600MW Childress build-out using S19 XP miners that have not yet been bought.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036123047077/ef20012021_ex99-1.htm) in full (23,783 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20012021_ex99-1.htm)

Quote: “30 EH/s Bitcoin mining program o Single site expansion, ongoing delivery and construction process”

View cached copy (2026-11-18)Live source ↗