Long Ridge plant nameplate to 505 MW

Company: Marathon Digital

Subject kind
facility capacity
Statement date
2026-11-17
Promised by
2026-12-31
Promised amount
505.0 MW
Current status
stated

The claim, verbatim

The Long Ridge plant had 485 MW of nameplate capacity in April and was expected to reach 505 MW in the second half of 2026.

Source (primary)

MARA sets a Nov. 27 close for its Long Ridge power plant purchase and prices $185 million of add-on notes - MLQ.ai (-, news_article)
View cached copy (2026-11-18)Live source ↗

Quote: “The plant had 485 MW of nameplate capacity in April and was expected to reach 505 MW in the second half of 2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms MARA sets a Nov. 27 close for its Long Ridge power plant purchase and prices $185 million of add-on notes - MLQ.ai

Quote: “The plant had 485 MW of nameplate capacity in April and was expected to reach 505 MW in the second half of 2026”

View cached copy (2026-11-18)Live source ↗