jain.com

Total contracted power capacity

Company: CleanSpark

Subject kind
facility capacity
Statement date
2025-02-05
Promised amount
853.0 MW
Current status
stated

The claim, verbatim

Total contracted power capacity of approximately 853 MW as of December 31, 2024

Source (primary)

CleanSpark 10-Q filed 2025-02-06 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “contracted power capacity of approximately 853 megawatts ("MW") as of December 31, 2024”

How we checked this

Checked on September 17, 2026. The cited source supports every part of this claim.

The 10-Q's company overview states a total contracted power capacity of approximately 853 MW as of December 31, 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000095017025015470/clsk-20241231.htm) in full (188,444 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark 10-Q filed 2025-02-06

Quote: “contracted power capacity of approximately 853 megawatts ("MW") as of December 31, 2024”

View cached copy (2026-08-31)Live source ↗