Alborz data center grid connection
Company: Cipher Mining
What the later record shows
Outcome not yet confirmed
Alborz appears only as an operating JV site and, later, as a divested JV site. No passage says whether or when its grid connection was completed.
“On February 19, 2026, we sold our 49% interests in our WindHQ JV sites to Canaan U.S. Inc.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cipher expects the grid connection at the Alborz data center in the first half of 2024.
Source (primary)
cipher-mining 8-K exhibit (cifr-ex99_2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Continued progress on grid connection at Alborz data center, expected 1H 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (cifr-ex99_2.htm)
Quote: “Continued progress on grid connection at Alborz data center, expected 1H 2024”