jain.com

Total operating capacity target of 10 EH/s

Company: IREN

Subject kind
guidance
Statement date
2023-11-29
Promised by
2024-06-30
Promised amount
10.0
Current status
verified

What the later record shows

Delivered on time · happened June 5, 2024

The June 5, 2024 update says operating hashrate had expanded to 10 EH/s, before the Q2 2024 deadline. The July update lists total operating capacity of 10 EH/s.

“Average operating hashrate of 9.4 EH/s (now expanded to 10 EH/s)”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗

Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Childress expansion is expected to support an increase in total company operating capacity to 10 EH/s by Q2 2024. This assumes future purchases of additional T21 miners, which have not yet been made.

Source (primary)

iren 8-K exhibit (ef20015516_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗

Quote: “supporting an increase in total Company operating capacity to 10 EH/s”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20015516_ex99-1.htm)

Quote: “supporting an increase in total Company operating capacity to 10 EH/s”

View cached copy (2026-11-16)Live source ↗

confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”

View cached copy (2026-11-01)Live source ↗

confirms iren 8-K exhibit (ef20030723_ex99-1.htm)

Quote: “Average operating hashrate of 9.4 EH/s (now expanded to 10 EH/s)”

View cached copy (2026-11-04)Live source ↗

Record of changes

November 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.