S21 and T21 miner shipments lift operating hashrate to 8.3 EH/s

Company: IREN

Subject kind
facility capacity
Statement date
2023-11-29
Promised by
2024-03-31
Promised amount
48.0 percent
Current status
verified

What the later record shows

Delivered; the record does not say when

By May 5, 2024 operating hashrate had grown beyond the 8.3 EH/s target to 9.4 EH/s. The March 2024 average was 7.1 EH/s, so it is unclear whether 8.3 EH/s was reached by March 31.

“Average operating hashrate of 8.2 EH/s (now expanded to 9.4 EH/s)”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗

Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The newly acquired 1.4 EH/s of S21 miners and 1.3 EH/s of T21 miners are scheduled to ship during Q1 2024. Once installed, they will raise operating hashrate by 48%, from 5.6 EH/s to 8.3 EH/s.

Source (primary)

iren 8-K exhibit (ef20015516_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗

Quote: “The newly acquired S21s (17.5 J/TH) and T21s (19 J/TH) are scheduled to be shipped during Q1 2024 and, once installed, will: • increase operating hashrate by 48% from 5.6 EH/s to 8.3 EH/s”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20015516_ex99-1.htm)

Quote: “The newly acquired S21s (17.5 J/TH) and T21s (19 J/TH) are scheduled to be shipped during Q1 2024 and, once installed, will: • increase operating hashrate by 48% from 5.6 EH/s to 8.3 EH/s”

View cached copy (2026-11-16)Live source ↗

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Average operating hashrate of 8.2 EH/s (now expanded to 9.4 EH/s)”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.