Kelowna HPC expansion capacity
Company: Hut 8
The claim, verbatim
Hut 8's HPC data centers have 4.1 MW of existing power capacity, with a further 1.5 MW of expansion capacity available within the existing Kelowna footprint.
Source (primary)
hut-8 8-K exhibit (tm2331643d4_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗
Quote: “Existing power capacity totals 4.1 MW, with a further 1.5 MW of expansion capacity available within existing space footprint in the Kelowna location”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms hut-8 8-K exhibit (tm2331643d4_ex99-2.htm)
Quote: “Existing power capacity totals 4.1 MW, with a further 1.5 MW of expansion capacity available within existing space footprint in the Kelowna location”