Planned MW and hashrate deployment for 2025

Company: Cipher Mining

Subject kind
facility capacity
Statement date
2025-02-24
Promised by
2025-12-31
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered on time · happened September 30, 2025

The additional ~150 MW (Black Pearl Phase I) was energized on schedule in Q2 2025, giving 477 MW of operating capacity including JV. Q3 2025 site hashrates sum to about 25.8 EH/s, above 25.2 EH/s.

“Phase I – 150 MW – Construction and energization completed on schedule in Q2 2025”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“477 MW Operating Capacity Including JV Capacity CURRENT OPERATIONS ~16.8 EH/s Q2 2025”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“~17.6 J/TH Fleet Efficiency ~11.3 EH/s Total Operating Hashrate $25,414 Q3 2025 All-In Electricity Cost per BTC(2) 150 MW Total Operating Power Capacity ~13.9 J/TH Fleet Efficiency ~10.1 EH/s Total Operating Hashrate”
2025-11-02 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-09-27)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Plan to deploy an additional approximately 150 MW for total of approximately 477 MW electrical capacity by end of 2025, with corresponding hashrate of at least approximately 25.2 EH/s

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “we plan to deploy an additional approximately 150 MW for a total of approximately 477 MW of electrical capacity by the end of 2025, and a corresponding hashrate of at least approximately 25.2 EH/s”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states the planned additional 150 MW, the 477 MW end-2025 total, and the corresponding hashrate of at least approximately 25.2 EH/s.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000005/cifr-20241231.htm) in full (492,885 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “we plan to deploy an additional approximately 150 MW for a total of approximately 477 MW of electrical capacity by the end of 2025, and a corresponding hashrate of at least approximately 25.2 EH/s”

View cached copy (2026-08-31)Live source ↗

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “~17.6 J/TH Fleet Efficiency ~11.3 EH/s Total Operating Hashrate $25,414 Q3 2025 All-In Electricity Cost per BTC(2) 150 MW Total Operating Power Capacity ~13.9 J/TH Fleet Efficiency ~10.1 EH/s Total Operating Hashrate”

View cached copy (2026-09-27)Live source ↗

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “Phase I – 150 MW – Construction and energization completed on schedule in Q2 2025”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.