Pipeline site energization

Company: Cipher Mining

Subject kind
facility timeline
Statement date
2025-02-24
Promised by
2025-05-31
Current status
verified

What the later record shows

Delivered late · new target June 30, 2025

On May 21, 2025 the company moved the planned 150 MW energization at its 300 MW pipeline site to June 2025. By August 2025 the 300 MW Black Pearl site in Wink, Texas had 150 MW operational, after the May target.

“including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025.”
2025-05-21 · Cipher Mining 424B5 filed 2025-05-22 View cached copy (2026-08-31)Live source ↗
“a 300 MW data center in Wink, Texas, of which 150 MW is operational as a bitcoin mining data center”
2025-08-06 · Cipher Mining 10-Q filed 2025-08-07 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Pipeline of seven additional sites in Texas, including one site expected to energize in May 2025

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “have a pipeline of seven additional sites in Texas, including one site expected to energize in May 2025”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K's business overview describes a pipeline of seven additional Texas sites, one of which is expected to energize in May 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000005/cifr-20241231.htm) in full (492,885 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “have a pipeline of seven additional sites in Texas, including one site expected to energize in May 2025”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 424B5 filed 2025-05-22

Quote: “including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025.”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 10-Q filed 2025-08-07

Quote: “a 300 MW data center in Wink, Texas, of which 150 MW is operational as a bitcoin mining data center”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.