jain.com

Barber Lake ERCOT interconnection approval

Company: Cipher Mining

Subject kind
regulatory
Statement date
2025-02-24
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Barber Lake Site has ERCOT interconnection approval for up to 300 MW

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Barber Lake Site has ERCOT interconnection approval of up to 300 MW”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000005/cifr-20241231.htm) in full (492,885 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “The Barber Lake Site has ERCOT interconnection approval of up to 300 MW”

View cached copy (2026-08-31)Live source ↗